Porcupinepine Park Avenue Bridge over the Juksei River

Construct new 140m long, 21.5m wide bridge over the Jukskei River
Client: Valuemax Northern Farms

R73 263 277.15

2020

Sandriver Bridge

Reconstruction of a bridge over the Sand River.
Client: Public Works EC

R57 404 579.59

2018

Replace Old Oak Bridge

Replacement of the Old Oak bridge over the N1, median barrier foundations and rehabilitation work.
Client: WCG – Transport and Public Works (Subcontract to Martin & East)

R50 549 362.30

2019

Porterville to Piketberg

Widening of 2No road over river bridges and 3No culverts.
Client: WCG – Transport and Public Works (Subcontract to Road-Mac Cape)

R29 793 642.36

2018

Val De Vie Bridge

Construction of a new bridge over the Berg River near Paarl.
Client: Val De Vie Investments (Pty) Ltd (Subcontract to NMC Civils)

R47 178 045.00

2018

Eteza Interchange

New interchange structure on N2 and Concrete road paving.
Client: SANRAL (Subcontract to Raubex KZN)

R52 594 036.40

2017

North West Province Bridges

Repairs of three low-level bridges.
Client: Bojanala District Municipality

R24 929 837.54

2016

Bridge over Bottelary River on Saxdowne Road

Construction of new road over river bridge.
Client: AMPHORIA (PTY) LTD

R8 270 037.20

2016

Libode Bridges

Construction of new interchange, new overpass, new underpass and new pedestrian bridge near Libode in the Eastern Cape.
Client: SANRAL (Subcontract to Triamic Construction)

R34 288 932.54

2016

Sandown Road over Rail Bridge

Construction of concrete road over rail bridge.
Client: Brink & Heath / CoCT

R13 526 024.99

2013

Widening of 4 Bridges from Kakemas to Keimoes

Widening of 4 bridges by 4m to accommodate the upgrade and widening of the N14.
Client: TOR Constuction / SANRAL

R20 882 231.58

2012

Bottelary Road Bridge over R300

Construction of new bridge for extra carriage way over the R300.
Client: Cilmor Trust

R13 618 742.21

2010

Bottelary Road Bridge over Kuilsrivier

Construction of new bridge for extra carriage way over the Kuils River.
Client: VDM Venter

R10 720 472.33

2010

Bosmansdam Pedestrian Bridge

Construction of new pedestrian bridge. Received Fulton Award.
Client: WCPA

R7 000 000.00

2006

Okavango Road over Road Bridges

2 new road over road bridges.
Client: WCPA

R1 500 000.00

2005

Road over Rail Bridge Beeshoek Mine

2 new road over rail bridges.
Client: Protekon

R3 500 000.00

2004